  Development :: Giriraj Parikrama
Giriraj Parikrama Development
Total Project Cost Rs 4.00 Crores
Expenditure incurred upto 15th April, 2011 Rs. 3.76 Crores
Work executed
  • 3.2 km. road constructed.
  • 28 Nos. CD works
  • Plantation works on North side done.
  • Boundary wall Constructed
  • One Chatari at the entrance constructed.
  • Plantation and Irrigation system on south side is under progress.
 